Stuyvesant High School Parents' Association
HomeAboutPublicationsCalendarNewsBulletinUpdates

Summary Meeting with the Board of Education and School Construction Authority
- July 12, 2002

Prepared by Tom Fusillo, Environmental Consultant for the PA, Principal, Environ, Co.

Represented at the meeting were the BOE (Bernie Orlan and Mohamed Hemida), the School Construction Authority [SCA] (Alex Lempert and Tony Freyre), the UFT (Chris Proctor, Ellie Engler and Tom Casimir), TDX Construction (Dunyo Awoonor), and Stuyvesant High School (Nicholas Mortenson). At the meeting, Alex Lempert of the SCA gave an overview of the proposed scope of the cleaning.

Overall, the proposed scope of work was generally consistent with the protocols developed by Howard Bader, and a number of those recommended protocols were specifically cited in the scope of work. Alex Lempert clarified one issue that was unclear in the scope of work documents that the BOE provided to ENVIRON on Monday. That was regarding the use of enclosures under negative air pressure around unit ventilators during cleaning of the unit ventilators. Mr. Lempert confirmed that enclosures will be used around all unit ventilators, including the horizontal ceiling-mounted unit ventilators.

There was also discussion about some additional items where the scope of work appeared to be inadequate. These included:

  1. Cleaning of all return ducts. According to Mr. Lempert, it was not intended to clean all returns ducts/plenums. At our request and that of Chris Proctor of the UFT, the BOE and SCA agreed that all return ducts and plenums will be cleaned.
  2. The scope of work specifically excluded cleaning of the linear diffusers located in the upper Auditorium ceiling. We and the UFT requested that those diffusers be included in the cleaning program and the BOE and SCA agreed to add them.
  3. Although the scope of work specified that wipe samples for lead would be collected from each unit ventilator after it was cleaned, there was no similar wipe sampling included for the HVAC system supply and return ducts after cleaning. We and the UFT requested that wipe samples for lead be collected from the ductwork for each major HVAC system after the completion of the cleaning of each system and the BOE and SCA agreed to add that sampling to the scope of work.
  4. The scope of work includes aggressive air sampling for analysis of asbestos and lead after the completion of the cleaning of each zone, but did not specify an action level for lead concentrations in air. It was agreed to use the USEPA criterion of 1.5 micrograms per cubic meter.
  5. It was requested that in addition to the replacement of the carpeting in the auditorium, the carpeting in the general office area should also be replaced and the BOE and SCA agreed.

The schedule for the cleaning operation begins tomorrow, when removal of unit ventilators on the 10th floor will begin. Concurrent cleaning of unit ventilators and the main HVAC systems will be performed. The current SCA schedule for the cleaning has the work completed by August 26, with any necessary follow-up work completed by August 31. There was some discussion regarding the implications of this schedule for the return of teachers and staff for the start of classes in September.

I forwarded the scope of work package that I received from the BOE to Howard Bader for his review. He and I spoke this afternoon and we agreed that the scope of work with the above modifications appears to be reasonably consistent with the recommendations that he had developed. We also discussed the inspections to be performed to evaluate the implementation of the scope of work and agreed to talk early next week to coordinate those inspections.

How to Help
Environmental Updates
In the Press
Photos after Sept 11